[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149201":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149201,802,2,"多选题","（2015 年真题）下列施工工序中，属于无粘结预应力施工工序的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预留管道",false,{"key":16,"text":17,"correct":18},"B","安装锚具",true,{"key":20,"text":21,"correct":18},"C","张拉",{"key":23,"text":24,"correct":14},"D","压浆",{"key":26,"text":27,"correct":18},"E","封锚","BCE","本题考查的是无粘结预应力施工工艺。预应力张拉分为先张法和后张法，后张法又分为有粘结力和无粘结力预应力。无粘结预应力中，由于钢筋都是被油脂和塑料保护层裹紧后浇筑到构件中的，所以相对于有粘结预应力来说，它没有预留孔道和压浆的工序。可参考教材水池无粘结预应力施工工艺流程：钢筋施工→安装内模板→铺设非预应力筋→安装托架筋、承压板、螺旋筋→铺设无粘结预应力筋→外模板→混凝土浇筑→混凝土养护→拆模及锚固肋混凝土凿毛→割断外露塑料套管并清理油脂→安装锚具→安装千斤顶→同步加压→量测→回油撤泵→锁定→切断无粘结筋（留100mm）→锚具及钢绞线防腐→封锚混凝土。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]