[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149192":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149192,802,2,"多选题","（2012 年真题）浅埋暗挖法中施工工期较长的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","全断面法",false,{"key":16,"text":17,"correct":14},"B","正台阶法",{"key":19,"text":20,"correct":21},"C","双侧壁导坑法",true,{"key":23,"text":24,"correct":21},"D","中洞法",{"key":26,"text":27,"correct":21},"E","柱洞法","CDE","本题考查的是喷锚暗挖法施工技术要求。采用浅埋暗挖法施工时，常见的典型施工方法是正台阶法以及适用于特殊地层条件的其他施工方法，相对来说工期较长的方法有双侧壁导坑法、交叉中隔壁法（CRD 工法）、中洞法、侧洞法、柱洞法。正台阶法工期短，全断面法工期最短。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]