[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149190":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149190,802,2,"多选题","（2010 年真题）关于盾构法隧道现场设施布置的手法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","盾构基座必须采用钢筋混凝土结构",false,{"key":16,"text":17,"correct":18},"B","采用泥水机械出土时，地面应设置水泵房",true,{"key":20,"text":21,"correct":18},"C","采用气压法施工时，地面应设置空压机房",{"key":23,"text":24,"correct":18},"D","采用泥水式盾构时，必须设置泥浆处理系统及中央控制室",{"key":26,"text":27,"correct":18},"E","采用土压式盾构时，应设置地面出土和堆土设施","BCDE","盾构施工的现场平面布置包括盾构工作竖井、竖井防雨棚及防淹墙、垂直运输设备、管片堆场、管片防水处理厂、拌浆站、料具间及机修间、两回路的变配电间等设施以及进出通道等。盾构施工现场设置：工作井施工需要采取降水措施时，应设相当规模的降水系统（水泵房）。（1）采用气压法盾构施工时，施工现场应设置空压机房，以供给足够的压缩空气。黑钻压卷，金考典软件考前一周更新，下载链接 www.jinkaodian.com（1）采用泥水平衡盾构施工时，施工现场应设置泥浆处理系统（中央控制室）、泥浆池。（2）采用土压平衡盾构施工时，应设置电机车电瓶充电间等设施。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]