[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149187":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149187,802,2,"多选题","（2012 年真题）盾构法隧道始发洞口土体常用的加固方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","注浆法",true,{"key":16,"text":17,"correct":14},"B","冻结法",{"key":19,"text":20,"correct":21},"C","SMW 法",false,{"key":23,"text":24,"correct":21},"D","地下连续墙法",{"key":26,"text":27,"correct":14},"E","高压喷射搅拌法","ABE","盾构法隧道始发洞口土体常用加固方法主要有注浆法、高压喷射搅拌法和冻结法。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]