[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149173":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149173,802,2,"多选题","（2010 年真题）关于现浇预应力混凝土连梁施工的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用支架法，支架验算的倾覆稳定系数不得小于1.3",true,{"key":16,"text":17,"correct":18},"B","采用移动模架法时，浇筑分段施工缝必须设在弯矩最大值部位",false,{"key":20,"text":21,"correct":14},"C","采用悬浇法时，挂篮与悬浇梁段混凝土的质量比值不应超过0.7",{"key":23,"text":24,"correct":14},"D","悬臂浇筑时，0 号段应实施临时固结",{"key":26,"text":27,"correct":14},"E","悬臂浇筑时，通常最后浇筑中跨合龙段","ACDE","验算模板、支架和拱架的抗倾覆稳定时，各施工阶段的稳定系数均不得小于1.3，故A 正确。采用移动模架法时，浇筑分段工作缝，必须设在弯矩零点附近，故B 错误，挂篮质量与梁段混凝土的质量比值控制在0.3-0.5，特殊情况下不得超过0.7，故C 正确。悬臂梁浇筑时，悬浇顺序及要求：（1）在墩顶托架或府架上浇筑0 号段并实施墩梁临时固结。（2）在0 号段山上安装悬臂挂篮，向两侧依次分段浇筑主梁至合龙前段。（3）在支架上浇筑边跨主梁合龙段。（4）最后浇筑中跨合龙段形成连续梁体系。（5）故DE 正确。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]