[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149172":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149172,802,2,"多选题","（2017 年真题）悬臂浇筑法施工连续梁合龙段时,应符合的规定有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合龙前，应在两端悬臂预加压重,直至施工完成后撤除",false,{"key":16,"text":17,"correct":18},"B","合龙前，应将合龙跨一侧墩的临时锚固放松",true,{"key":20,"text":21,"correct":18},"C","合龙段的混凝土强度提高一级的主要目的是尽早施加预应力",{"key":23,"text":24,"correct":14},"D","合龙段的长度可为2m",{"key":26,"text":27,"correct":14},"E","合龙段应在一天中气温最高时进行","BC","A 项应为“合龙前，在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除，以使悬臂端挠度保持稳定”。D 项应为“合龙段的长度宜为2m”。E 项应为“合龙宜在一天中气温最低时进行”。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]