[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149167":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149167,802,2,"多选题","（2015 年真题）现浇钢筋混凝土预应力箱梁模板支架刚度验算时，在冬期施工的荷载组合包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","模板、支架自重",true,{"key":16,"text":17,"correct":14},"B","现浇箱梁自重",{"key":19,"text":20,"correct":21},"C","施工人员、堆放施工材料荷载",false,{"key":23,"text":24,"correct":14},"D","风雪荷载",{"key":26,"text":27,"correct":21},"E","倾倒混凝土时产生的水平冲击荷载","ABD","本题考查的是模板、支架和拱架的设计与验算、设计模板、支架和拱架刚度验算时的荷载组合包括：模板、拱架和支架自重；新浇筑混凝土、钢筋混凝土或圬工砌体的自重力；设于水中的支架所承受的水流压力、波浪力、流水压力、船只及其漂浮物的撞击力；其他可能产生的荷载、冬期施工保温设施荷载等。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]