[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149155":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149155,802,2,"多选题","（2019 年真题）关于填土路基施工要点的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","原地面标高低于设计路基标高时，需要填筑土方",true,{"key":16,"text":17,"correct":18},"B","土层填筑后，立即采用8t 级压路机碾压",false,{"key":20,"text":21,"correct":14},"C","填筑时，应妥善处理井穴、树根等",{"key":23,"text":24,"correct":14},"D","填方高度应按设计标高增加预沉量值",{"key":26,"text":27,"correct":18},"E","管涵顶面填土300mm 以上才能用压路机碾压","ACD","填土路基当原地面标高低于设计路基标高时，需要填筑土方（即填方路基）。（1）排除原地面积水，清除树根、杂草、淤泥等。应妥善处理坟坑、井穴、树根坑的坑槽，分层填实至原地面高。（2）填方段内应事先找平，当地面坡度陡于1∶5 时，需修成台阶形式，每层台阶高度不宜大于300mm，宽度不应小于1.0m。（3）根据测量中心线桩和下坡脚桩，分层填土、压实。（4）碾压前检查铺筑土层的宽度、厚度及含水量，合格后即可碾压，碾压“先轻后重”，最后碾压应采用不小于12t 级的压路机。（5）填方高度内的管涵顶面填土500mm 以上才能用压路机碾压。（6）路基填方高度应按设计标高增加预沉量值。填土至最后一层时，应按设计断面、高程控制填土厚度并及时碾压修整。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]