[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149153,802,2,"多选题","（2010 年真题）城市道路土质路基压实的原则有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","先轻后重",true,{"key":16,"text":17,"correct":14},"B","先慢后快",{"key":19,"text":20,"correct":14},"C","先静后振",{"key":22,"text":23,"correct":14},"D","轮迹重叠",{"key":25,"text":26,"correct":27},"E","先高后低",false,"ABCD","土质路基压实原则：先轻后重、先静后振、先低后高、先慢后快、轮迹重叠。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]