[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149126,802,1,"单选题","盾构法隧道掘进速度不必与地表控制的()相协调。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","侧面土压平衡调整值",true,{"key":16,"text":17,"correct":18},"B","进出土量",false,{"key":20,"text":21,"correct":18},"C","隆陷值",{"key":23,"text":24,"correct":18},"D","同步注浆","2020教材P466 \u002F 2019教材P467 盾构掘进速度,应与地表控制的隆陷值、进出土量、正面土压平衡调整值及同步注浆等相协调。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]