[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149122,802,1,"单选题","索鞍安装时应根据设计提供的( )就位，在加劲梁架设、桥面铺装过程中应按设计提供的数据逐渐顶推到永久位置。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预偏量",true,{"key":16,"text":17,"correct":18},"B","设计位置",false,{"key":20,"text":21,"correct":18},"C","施工位置",{"key":23,"text":24,"correct":18},"D","顶推量","2020教材P465 \u002F 2019教材P466 （1）索鞍安装应选择在晴朗的白天连续完成。安装时应根据设计提供的预偏量就位，在加劲梁架设、桥面铺装过程中应按设计提供的数据逐渐顶推到永久位置。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]