[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1149121,802,1,"单选题","水泥混凝土道路在面层混凝土（ ）达到设计强度，且填缝完成前，不得开放交通。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","抗压强度",false,{"key":16,"text":17,"correct":14},"B","抗拉强度",{"key":19,"text":20,"correct":14},"C","抗折强度",{"key":22,"text":23,"correct":24},"D","弯拉强度",true,"2020教材P464 \u002F 2019教材P465 水泥混凝土道路在面层混凝土弯拉强度达到设计强度，且填缝完成前，不得开放交通。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]