[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149079":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1149079,802,1,"单选题","以下关于竖井土方开挖安全控制要点说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竖井临近各类管线、建（构）筑物时，应对管线、建（构）筑物采取加固措施",false,{"key":16,"text":17,"correct":18},"B","采用先开挖后支护方式时，随开挖随支护，随支护随开挖，均衡施工",true,{"key":20,"text":21,"correct":14},"C","吊装出土时，土方容器下降落稳后，施工人员方可靠近作业",{"key":23,"text":24,"correct":14},"D","发现坍塌征兆时，必须停止作业，施工人员撤至安全地带","2020教材P444 \u002F 2019教材P445 （二）工作井土方开挖（2）采用先开挖后支护方法时，应按施工组织设计的规定，由上至下分层进行，随开挖随支护。支护结构达到规定要求后，方可开挖下一层土方。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]