[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149074":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1149074,802,1,"单选题","下列关于在特殊地段和特殊地质条件下盾构施工安全措施说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工单位制定专项施工方案",false,{"key":16,"text":17,"correct":14},"B","合理设定开挖面压力，控制地层变形",{"key":19,"text":20,"correct":14},"C","根据工程水文地质条件，确定同步注浆的材料、压力和流量",{"key":22,"text":23,"correct":24},"D","必须精减监测测点、降低监测频率，并根据监测结果调整掘进参数",true,"2020教材P442 \u002F 2019教材P443 特殊地段及特殊地质条件下掘进：（5）必要时加密监测测点、提高监测频率，并根据监测结果及时调整掘进参数。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]