[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149073":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1149073,802,1,"单选题","下列关于盾构机穿越江河段施工说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设定适当的开挖面压力，加强开挖面管理与掘进参数控制，防止冒浆和坍塌",false,{"key":16,"text":17,"correct":14},"B","盾构密封系统进行全面检查和处理",{"key":19,"text":20,"correct":21},"C","加强对地层变形监测",true,{"key":23,"text":24,"correct":14},"D","采用快凝早强注浆材料，加强同步注浆和二次补充注浆","2020教材P442 \u002F 2019教材P443 （8）穿越江河地段施工应详细查明工程地质和水文地质条件和河床状况，设定适当的开挖面压力，加强开挖面管理与掘进参数控制，防止冒浆和地层坍塌；并对盾构密封系统进行全面检查和处理；配备足够的排水设备与设施。穿越过程中，采用快凝早强注浆材料，加强同步注浆和二次补充注浆。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]