[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1149072,802,1,"单选题","以下关于盾构施工时邻近既有建（构）筑物安全控制要点说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位分析、预测、确定建（构）筑物的容许极限变形值",false,{"key":16,"text":17,"correct":18},"B","依据建筑物基础结构类型采取加固或托换措施",true,{"key":20,"text":21,"correct":14},"C","穿越过程中，加强既有建（构）筑物受力变化观测",{"key":23,"text":24,"correct":14},"D","地层变形超过施工管理值，应立即采取保护措施","2020教材P442 \u002F 2019教材P443 （7）穿越或邻近建（构）筑物施工前应对建（构）筑物进行详细调查，评估施工对建（构）筑物的影响，并采取相应的保护措施。根据建（构）筑物基础与结构的类型、现状，可采取加固或托换措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]