[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149060":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1149060,802,1,"单选题","箱涵顶进在穿越铁路路基时，必须对铁道线路进行适当加固并（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","降低顶进速度",false,{"key":16,"text":17,"correct":14},"B","临时封闭线路",{"key":19,"text":20,"correct":21},"C","限制列车车速",true,{"key":23,"text":24,"correct":14},"D","加固路基","2020教材P433 \u002F 2019教材P434 三、（一）.（1）限制铁路列车通过施工区域的速度，限制或者疏导路面交通。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]