[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149059,802,1,"单选题","箱涵顶进穿越铁路路基时，应（ ）开挖和顶进。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在列车运行间隙",true,{"key":16,"text":17,"correct":18},"B","连续",false,{"key":20,"text":21,"correct":18},"C","快速",{"key":23,"text":24,"correct":18},"D","慢速","2020教材P434 \u002F 2019教材P435 （二）（3）在列车运行间隙或避开交通高峰期开挖和顶进；列车通过时，严禁挖土作业，人员应撤离开挖面。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]