[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1149058,802,1,"单选题","桥梁拆除初步施工组织设计制定过程中，应针对结构体系、类型不同而采取不同的拆除方法，结合（ ），安排拆除步骤，控制拆除过程的结构内力。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计图纸要求",false,{"key":16,"text":17,"correct":14},"B","原结构施工方法",{"key":19,"text":20,"correct":21},"C","计算分析",true,{"key":23,"text":24,"correct":14},"D","桥梁病害严重程度","2020教材P435 \u002F 2019教材P436 （三）（2）应结合计算分析，安排拆除步骤和控制拆除过程的结构内力。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]