[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149057,802,1,"单选题","对复杂结构的桥梁或拆除过程复杂、困难的情况，应该采取（ ）手段，确保施工安全。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","仪器监测",true,{"key":16,"text":17,"correct":18},"B","计算分析",false,{"key":20,"text":21,"correct":18},"C","体系转换",{"key":23,"text":24,"correct":18},"D","局部临时加固","2020教材P436 \u002F 2019教材P437 （二）2.对复杂结构的桥梁或拆除过程复杂、困难的情况，应该采取监控手段（如仪器监测），通过必要的计算分析，对标高、变形、应力实时控制，及时反馈施工操作人员。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]