[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149055,802,1,"单选题","施工单位与建设单位在签订拆除工程的施工合同时，应签订安全生产管理协议，明确双方的安全管理责任，其中施工单位应对拆除工程的（ ）负直接责任。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安全技术管理",true,{"key":16,"text":17,"correct":18},"B","环境保护",false,{"key":20,"text":21,"correct":18},"C","地下管线保护",{"key":23,"text":24,"correct":18},"D","施工安全过程检查","2020教材P436 \u002F 2019教材P437 （一）（1）施工单位与建设单位在签订拆除工程的施工合同时，应签订安全生产管理协议，明确双方的安全管理责任。施工单位应对拆除工程的安全技术管理负直接责任;建设单位、监理单位应对拆除工程施工安全负检查督促责任。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]