[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1149052,802,1,"单选题","爆破拆除工程应进行（ ）并经当地有关部门审核批准后方可实施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安全技术方案制定",false,{"key":16,"text":17,"correct":14},"B","方案的专家论证",{"key":19,"text":20,"correct":14},"C","地下管线保护",{"key":22,"text":23,"correct":24},"D","安全评估",true,"2020教材P438 \u002F 2019教材P439 3.（1）爆破拆除工程应做出安全评估并经当地有关部门审核批准后方可实施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]