[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149027":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1149027,802,1,"单选题","关于柔性管道回填，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","柔性管道的沟槽回填质量控制是管道工程施工质量控制的关键",false,{"key":16,"text":17,"correct":14},"B","现场试验段主要用以确定压实机械和施工参数",{"key":19,"text":20,"correct":21},"C","在设计的管基有效支承角范围必须用中、粗砂、黏土填充密实，与管壁紧密接触",true,{"key":23,"text":24,"correct":14},"D","回填作业每层的压实遍数，按压实度要求、压实工具、虚铺厚度和含水量，经现场试验确定","2020教材P396 \u002F 2019教材P397 （4）管基有效支承角范围内应采用中粗砂填充密实，与管壁紧密接触，不得用土或其他材料填充。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]