[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149022,802,1,"单选题","热力管道保温施工时，同层的预制管壳应（ ），内、外层应（ ），外层的水平接缝应在（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","错缝；压缝；侧面",true,{"key":16,"text":17,"correct":18},"B","错缝；齐缝；底面",false,{"key":20,"text":21,"correct":18},"C","压缝；错缝；侧面",{"key":23,"text":24,"correct":18},"D","压缝；齐缝；底面","2020教材P393 \u002F 2019教材P394 同层的预制管壳应错缝，内、外层应压缝，搭接长度应大于100mm，拼缝应严密，外层的水平接缝应在侧面。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]