[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1149020,802,1,"单选题","非水平热力管道的绝热施工应（ ）进行，防潮层和保护层的搭接应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自下而上；下压上",false,{"key":16,"text":17,"correct":14},"B","自上而下；下压上",{"key":19,"text":20,"correct":14},"C","自上而下；上压下",{"key":22,"text":23,"correct":24},"D","自下而上；上压下",true,"2020教材P393 \u002F 2019教材P394 保温层厚度超过100mm时，应分两层或多层逐层施工，各层的厚度应接近，非水平管道的保温施工应自下而上进行，防潮层和保护层的搭接应上压下，搭接宽度不小于30mm。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]