[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1149011,802,1,"单选题","关于施工现场对热熔连接焊接接头质量进行检验，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","100％翻边对称性检验和不少于30％的翻边切除对正性检验",false,{"key":16,"text":17,"correct":14},"B","30％翻边对称性检验和不少于10％的翻边切除对正性检验",{"key":19,"text":20,"correct":14},"C","30％翻边对称性检验和不少于30％的翻边切除的对正性检验",{"key":22,"text":23,"correct":24},"D","100％的翻边对称性检验和不少于10％的翻边切除的对正性检验",true,"2020教材P392 \u002F 2019教材P393 （一）热熔连接：（4）热熔连接后，应对全部接头进行外观检查和不少于10%的翻边切除检验。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]