[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149003":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1149003,802,1,"单选题","下列关于焊接作业执行文件说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照企业有关技术人员审批的工艺指导书执行",true,{"key":16,"text":17,"correct":18},"B","按照企业有关技术人员审批的焊接工艺评定执行",false,{"key":20,"text":21,"correct":18},"C","按照企业有关技术人员审批的焊接工艺手册执行",{"key":23,"text":24,"correct":18},"D","按照企业及业主审批的焊接专项施工方案执行","2020教材P391 \u002F 2019教材P392 二、管道焊接质量控制：（一）焊接前质量控制：（3）首次使用的管材、焊材以及焊接方法应在施焊前进行焊接工艺评定，制定焊接工艺指导书，焊接作业必须按焊接工艺指导书的要求进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]