[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148990,802,1,"单选题","给水排水构筑物施工时，应按（ ）的顺序施工，并应防止各构筑物交叉施工时相互干扰。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先地上后地下、先深后浅",false,{"key":16,"text":17,"correct":14},"B","先地下后地上、先浅后深",{"key":19,"text":20,"correct":21},"C","先地下后地上、先深后浅",true,{"key":23,"text":24,"correct":14},"D","先地上后地下、先浅后深","2020教材P376 \u002F 2019教材P378 二、施工应采取的措施：（1）给水排水构筑物施工时，应按“先地下后地上，先深后浅”的顺序施工，并应防止各构筑物交叉施工时相互干扰。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]