[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148989,802,1,"单选题","在下列采取的混凝土防裂缝技术措施中，不属于设计措施的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","控制结构断面配筋率，增加构造配筋，提高结构抗裂性能",false,{"key":16,"text":17,"correct":14},"B","保持结构断面尺寸均匀，结构变化部位采用过渡形式，减少结构应力集中现象",{"key":19,"text":20,"correct":14},"C","设置变形缝，控制裂缝的产生",{"key":22,"text":23,"correct":24},"D","进行混凝土配合比设计，提高混凝土早期抗裂性能",true,"2020教材P376 \u002F 2019教材P377 一、设计应考虑的主要措施：（1）合理增配构造（钢）筋，提高结构抗裂性能。构造配筋应尽可能采用小直径、小间距。全断面的配筋率不小于0.3%。（2）避免结构应力集中。避免结构断面突出产生的应力集中，当不能避免断面突变时，应做局部处理，设计成逐渐变化的过渡形式。（3）按照设计规范要求，设置变形缝或结构单元。如果变形缝赶出规范规定的长度时，应采取有效的防开裂措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]