[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148985,802,1,"单选题","在（ ）管片拼装时，应根据特殊管片的设计位置，预先调整好盾构姿态和盾尾间隙，管片拼装符合设计要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","曲线段",false,{"key":16,"text":17,"correct":18},"B","特殊位置",true,{"key":20,"text":21,"correct":14},"C","直线段",{"key":23,"text":24,"correct":14},"D","特殊地层","2020教材P375 \u002F 2019教材P376 （6）在特殊位置管片拼装时，应根据特殊管片的设计位置，预先调整好盾构姿态和盾尾间隙，管片拼装符合设计要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]