[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148984,802,1,"单选题","根据实际情况采取地面预注浆、隧道内小导管注浆和衬砌结构背后注浆等措施，控制（ ）在允许范围。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地层变形",true,{"key":16,"text":17,"correct":18},"B","拱顶变形",false,{"key":20,"text":21,"correct":18},"C","收敛变形",{"key":23,"text":24,"correct":18},"D","地面变形","2020教材P372 \u002F 2019教材P373 （四）2.减少地面沉降措施（2）根据实际情况采取地面预注浆、隧道内小导管注浆和衬砌结构背后注浆等措施，控制地层变形在允许范围。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]