[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148980":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148980,802,1,"单选题","对关键部位、特殊工艺和（ ）专项工程分别编制专项施工方案和质量保证措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暗挖工程",false,{"key":16,"text":17,"correct":18},"B","危险性较大",true,{"key":20,"text":21,"correct":14},"C","大模板工程",{"key":23,"text":24,"correct":14},"D","吊装过程","2020教材P370 \u002F 2019教材P371 （二）质量保证计划（2）对关键部位、特殊工艺、危险性较大分项工程分别编制专项施工方案和质量保证措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]