[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148978,802,1,"单选题","关于基坑开挖说法，以下说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基底经勘察，设计，监理，施工单位验收合格后，应及时施工混凝土垫层",false,{"key":16,"text":17,"correct":14},"B","开挖至邻近基底200mm时，应配合人工清底，不得超挖或扰动基底土",{"key":19,"text":20,"correct":14},"C","钢筋网片安装及喷射混凝土紧跟开挖流水段，及时施工支撑或锚杆",{"key":22,"text":23,"correct":24},"D","土方必须自下而上分层、分段依次开挖",true,"2020教材P367 \u002F 2019教材P369 （一）基坑开挖施工 （2）土方必须自上而下分层、分段依次开挖，钢筋网片安装及喷射混凝土紧跟开挖流水段，及时施工支撑或锚杆，开挖至邻近基底200mm时，应配合人工清底，不得超挖或扰动基底土。 基底经勘察，设计，监理，施工单位验收合格后，应及时施工混凝土垫层",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]