[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148977":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148977,802,1,"单选题","钢管混凝土拱应采用（ ）施工，由拱脚向拱顶对称均衡地连续压注一次完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","泵送降压法",false,{"key":16,"text":17,"correct":18},"B","泵送顶升压注法",true,{"key":20,"text":21,"correct":14},"C","泵车浇筑法",{"key":23,"text":24,"correct":14},"D","千斤顶压法","2020教材P365 \u002F 2019教材P367 （二）浇筑作业（1）应采用泵送顶升压注施工，由两拱脚至拱顶对称均衡地连续压注一次完成。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]