[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148975,802,1,"单选题","预应力筋张拉前应根据设计要求对孔道的（ ）进行实测，以便确定张拉控制应力，并确定预应力筋的理论伸长值。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","摩阻损失",true,{"key":16,"text":17,"correct":18},"B","直径",false,{"key":20,"text":21,"correct":18},"C","强度",{"key":23,"text":24,"correct":18},"D","长度","2020教材P364 \u002F 2019教材P366 （二）张拉与锚固（2）张拉前应根据设计要求对孔道的摩阻损失进行实测，以便确定张拉控制应力，并确定预应力筋的理论伸长值。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]