[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148963,802,1,"单选题","（ ）施工时，严控混凝土的配合比，保证其和易性，必要时可适当掺加缓凝剂。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","冬季",false,{"key":16,"text":17,"correct":14},"B","雨季",{"key":19,"text":20,"correct":14},"C","春季",{"key":22,"text":23,"correct":24},"D","夏季",true,"2020教材P355 \u002F 2019教材P357 （二）高温施工的规定（1）严控混凝土的配合比，保证其和易性，必要时可适当掺加缓凝剂，特高温时段混凝土拌合可掺加降温材料。尽量避开气温过髙的时段，可选晚间施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]