[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148962,802,1,"单选题","沥青混合料面层不得在雨、雪天气及环境最高温度低于（ ）时施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","-5℃",false,{"key":16,"text":17,"correct":14},"B","8℃",{"key":19,"text":20,"correct":21},"C","5℃",true,{"key":23,"text":24,"correct":14},"D","10℃","2020教材P354 \u002F 2019教材P356 （四）沥青混凝土面层（1）城市快速路、主干路的沥青混合料面层在低于5℃时禁止施工。次干路及其以下道路在施工温度低于5℃时，应停止施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]