[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148961,802,1,"单选题","水泥稳定土（粒料）类基层进入冬期时，应在基层施工时向基层材料中掺入（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","缓凝剂",false,{"key":16,"text":17,"correct":14},"B","速凝剂",{"key":19,"text":20,"correct":21},"C","防冻剂",true,{"key":23,"text":24,"correct":14},"D","温热水","2020教材P354 \u002F 2019教材P356 （三）（2）水泥稳定土（粒料）类基层，宜在进入冬期前15~30d停止施工。当上述材料养护期进入冬期时，应在基层施工时向基层材料中掺入防冻剂。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]