[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148951,802,1,"单选题","施工过程质量控制中，不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成品质量控制",true,{"key":16,"text":17,"correct":18},"B","分项工程（工序）控制",false,{"key":20,"text":21,"correct":18},"C","特殊过程控制",{"key":23,"text":24,"correct":18},"D","不合格产品控制","2020教材P347 \u002F 2019教材P349 二、（一）分项工程（工序）控制（二）特殊过程控制（三）不合格产品控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]