[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148950,802,1,"单选题","施工质量控制中，进行不合格让步接收时，工程施工项目部应向（ ）提出书面让步接收申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包方",true,{"key":16,"text":17,"correct":18},"B","监理",false,{"key":20,"text":21,"correct":18},"C","总包方",{"key":23,"text":24,"correct":18},"D","质量监督部门","2020教材P347 \u002F 2019教材P349 （三）（5）进行不合格让步接收时，工程施工项目部应向发包方提出书面让步接收申请，记录不合格程度和返修的情况，双方签字确认让步接收协议和接收标准。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]