[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148949,802,1,"单选题","对于特殊过程的质量控制，以下说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对工程施工项目质量计划规定的特殊过程，可不设置质量控制点",false,{"key":16,"text":17,"correct":18},"B","编制的作业指导书，应经项目部或企业技术负责人审批后执行。",true,{"key":20,"text":21,"correct":14},"C","不太成熟的工艺应安排试验，编制成作业指导书，根据情况进行首件（段）验收",{"key":23,"text":24,"correct":14},"D","编制的作业指导书，应经监理工程师审批后执行","2020教材P347 \u002F 2019教材P349 （二）特殊过程控制 （1）依据一般过程质量控制要求编制针对性作业指导书。 （2）编制的作业指导书，应经项目部或企业技术负责人审批后执行。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]