[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148946,802,1,"单选题","实行分包的分项、分部工程，应制定（ ）和质量保证措施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量计划",false,{"key":16,"text":17,"correct":14},"B","质量目标",{"key":19,"text":20,"correct":14},"C","质量控制",{"key":22,"text":23,"correct":24},"D","质量验收程序",true,"2020教材P344 \u002F 2019教材P346 （4）实行分包的分项、分部工程：应制定质量验收程序和质量保证措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]