[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148940,802,1,"单选题","工程项目进度执行情况的综合描述，不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","报告的起止期",false,{"key":16,"text":17,"correct":14},"B","原定目标",{"key":19,"text":20,"correct":14},"C","实际完成情况",{"key":22,"text":23,"correct":24},"D","进度检查",true,"2020教材P340 \u002F 2019教材P342 二（二）（1）工程项目进度执行情况的综合描述。主要内容是：报告的起止日期，当地气象及晴雨天数统计；施工计划的原定目标及实际完成情况；报告计划期内现场的主要大事记。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]