[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148939,802,1,"单选题","跟踪工程部位的（ ），以便对工程量、总产值、耗用的人工、材料和机械台班等的数量进行统计与分析。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","形象进度",true,{"key":16,"text":17,"correct":18},"B","计划变更",false,{"key":20,"text":21,"correct":18},"C","分包进度",{"key":23,"text":24,"correct":18},"D","计划进度","2020教材P339 \u002F 2019教材P341 一（4）跟踪工程部位的形象进度，对工程量、总产值、耗用的人工、材料和机械台班等的数量进行统计与分析，以指导下一步工作安排；并编制统计报表。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]