[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148937,802,1,"单选题","工程项目施工进度计划在实施过程中进行必要调整的依据是施工进度（ ）结果。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","月度检查",false,{"key":16,"text":17,"correct":14},"B","例行统计",{"key":19,"text":20,"correct":21},"C","检查审核",true,{"key":23,"text":24,"correct":14},"D","现场巡视","2020教材P339 \u002F 2019教材P341 三、（2）施工进度计划在实施过程中进行的必要调整必须依据施工进度计划检查审核结果进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]