[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148936,802,1,"单选题","月、旬（或周）施工进度计划是（ ）性作业计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制",false,{"key":16,"text":17,"correct":14},"B","基础",{"key":19,"text":20,"correct":21},"C","实施",true,{"key":23,"text":24,"correct":14},"D","阶段","2020教材P339 \u002F 2019教材P341 二、2.实施性计划月、旬（或周）施工进度计划是实施性的作业计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]