[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148935,802,1,"单选题","在工程实施过程中，对进度计划的调整的依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度计划变更单",false,{"key":16,"text":17,"correct":14},"B","业主的指令",{"key":19,"text":20,"correct":14},"C","监理的指令",{"key":22,"text":23,"correct":24},"D","进度计划检查审核结果",true,"2020教材P339 \u002F 2019教材P341 （2）施工进度计划在实施过程中进行的必要调整必须依据施工进度计划检查审核结果进行。调整内容应包括：工程量、起止时间、持续时间、工作关系、资源供应。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]