[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148934,802,1,"单选题","项目进度控制总目标可按单位工程分解为（ ）分目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","交工",true,{"key":16,"text":17,"correct":18},"B","竣工",false,{"key":20,"text":21,"correct":18},"C","时间",{"key":23,"text":24,"correct":18},"D","专业","2020教材P339 \u002F 2019教材P340 一、施工进度目标控制（2）按单位工程分解为交工分目标，制定子单位工程或分部工程交工目标。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]