[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148933,802,1,"单选题","分包人的施工进度计划应是承包人施工总进度计划的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基础",false,{"key":16,"text":17,"correct":18},"B","控制范畴",true,{"key":20,"text":21,"correct":14},"C","依据",{"key":23,"text":24,"correct":14},"D","组成部分","2020教材P339 \u002F 2019教材P340 （二）（2）承包单位应将分包的施工进度计划纳人总进度计划的控制范畴。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]