[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148921,802,1,"单选题","工程施工阶段按照施工（ ）要求，设置道路、组织排水、搭建临时设施、堆放物料和停放机具设备等。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","围挡面积",false,{"key":16,"text":17,"correct":14},"B","现场需要",{"key":19,"text":20,"correct":14},"C","工期安排",{"key":22,"text":23,"correct":24},"D","总平面图",true,"2020教材P325 \u002F 2019教材P327 （一）（3）工程施工阶段按照施工总平面图要求，设置道路、组织排水、搭建临时设施、堆放物料和停放机具设备等。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]